Recent Project Completion

Tauriko School Refurbishment

This project was initiated by the Board of Trustees and the Ministry of Education as part of the school’s 10-Year Property Plan (10YPP), with funding allocated through the 5-Year Agreement (5YA).

A lead designer was engaged to oversee the refurbishment works, and Facilitate Group was appointed as the main contractor following an open tender process. The scope of work involved completely refurbishing two classrooms, transforming them into modern learning spaces with breakout areas.

This comprehensive internal renovation was completed within a construction period of just nine weeks.

tauriko school refurbished wall front project

Project Services

Project Objectives & Constraints

Working in an active school environment posed unique risks, further complicated by the discovery of asbestos, which impacted project costs and caused programme delays. The primary objective was to mitigate these challenges while ensuring the successful completion of the project. This required effectively managing client expectations, budgets, and risks throughout.

Project Outcome

We enhanced the learning environment in Rooms 5 and 6 with a complete internal refurbishment, including the creation of a dedicated breakout space designed to support specific and focused learning outcomes.